Justia Real Estate & Property Law Opinion Summaries

Articles Posted in US Court of Appeals for the Sixth Circuit
by
In this case, Norfolk Southern Railway Company and Dille Road Recycling, LLC disputed over a narrow parcel of land adjacent to Norfolk’s active rail line in Euclid, Ohio. Although Norfolk owned the land, Dille had been using it for nearly two decades. The parties took the matter to federal court after negotiations failed. Dille sought to claim the parcel through adverse possession or a prescriptive easement, while Norfolk argued that Dille’s property claims were preempted by the Interstate Commerce Commission Termination Act (ICCTA). The district court held that Dille’s prescriptive-easement claim was not preempted and granted Dille the easement.The United States Court of Appeals for the Sixth Circuit reversed the district court's decision, ruling that federal law preempted Dille’s state-law prescriptive-easement claim. The court determined that the easement Dille sought was so exclusive and conflicting that it was essentially adverse possession by another name. The court noted that while Dille claimed the easement was nonexclusive, the reality was that Dille's use of the parcel did not allow for shared use with Norfolk. The court also found that Dille's proposed use of the parcel was much closer to the complete taking of the property, which would unreasonably interfere with rail transportation and therefore was preempted by the ICCTA. The court reasoned that the possession or conflicting use of railroad property can be burdensome even if the railroad is not currently using the contested property. The case was remanded for further proceedings consistent with the opinion. View "Norfolk Southern Railway Co. v. Dille Road Recycling, LLC" on Justia Law

by
In March 2015, Jere Hinman hired BrightView Landscape Development, Inc., to design and construct a pool at her residence. BrightView subcontracted with Georgia Gunite and Pool Company, Inc., to install plumbing and spray shotcrete for the pool shell. In November 2015, Hinman contacted BrightView after receiving an unusually high water bill and discovered that the pool was leaking water due to a missing part that was not included in Georgia Gunite’s scope of work. BrightView and Georgia Gunite worked together to address the issue in April 2016. In 2018, Hinman sued BrightView for defective construction of the pool, and BrightView filed a third-party complaint against Georgia Gunite, seeking indemnification based on the subcontractor agreement. Georgia Gunite moved for summary judgment, arguing that BrightView's claim was barred by Tennessee's four-year statute of repose for actions alleging defective improvements to real estate.The United States Court of Appeals affirmed the decision of the District Court for the Middle District of Tennessee, which granted summary judgment in favor of Georgia Gunite. The court held that, although BrightView's indemnification claim against Georgia Gunite was contractual in nature, it fell within the scope of Tennessee's statute of repose for deficient construction of an improvement to real property because, at its core, it sought to recover damages arising from such deficient construction. The court rejected BrightView's argument that the statute of repose only applies to tort actions. The court also rejected BrightView's argument that the application of the statute of repose in this case would extinguish its claim before it even accrued, noting that this argument is directed at the nature of a statute of repose. The court further held that the repose statute is not mutually exclusive with statutes of limitation. Thus, BrightView's claim against Georgia Gunite was barred because it was not brought within four years after substantial completion of the pool construction. View "Hinman v. ValleyCrest Landscaping Dev." on Justia Law

by
Michigan’s Uniform Unclaimed Property Act (UUPA) allows the state to take custody—not ownership—of unclaimed property “in trust for the benefit of the rightful owner” After publishing required notices, the state sells or liquidates the unclaimed property within three years of receiving it, unless the owner brings a valid claim, then deposits the proceeds into its general fund, subtracting reasonable administration costs; the owner can no longer reclaim his property, but can still recover the “net proceeds” from its sale. UUPA apermits owners to recover the interest earned on their property and post-liquidation interest if the property accrued interest before the state took custody of it.Two companies delivered O’Connor’s properties—checks collectively worth no more than $350— to the state after he failed to claim them. The state liquidated them. O’Connor filed a claim for compensation. Michigan reimbursed O’Connor for the value of his property, but not any post-liquidation interest. O’Connor alleges that neither the state nor the third-party holders provided him with the statutorily required notices. O’Connor sued Michigan under the Fifth Amendment; Michigan’s Treasurer, and the Administrative Manager of the Unclaimed Property Program, under 42 U.S.C. 1983. The Sixth Circuit held that the officials are entitled to qualified immunity on O’Connor’s taking claims but not his due process claims. The district court correctly dismissed O’Connor’s claims against the state but should not have dismissed them with prejudice. View "O'Connor v. Eubanks" on Justia Law

by
Built in 1924, the Edenville Dam near Midland, Michigan, has earthen embankments spanning the Tittabawassee and Tobacco Rivers, forming a 2,600-acre reservoir. In 1998, the Federal Energy Regulatory Commission (FERC) issued a license to Wolverine Power to operate the Dam. FERC directed Wolverine to increase the Dam’s spillway capacity. Wolverine became insolvent. In 2003, Boyce’s predecessor purchased Wolverine’s license. Boyce promised to increase spillway capacity but failed to do so and committed numerous other regulatory violations: unauthorized repairs, dredging, and land-clearing; failing to file a public safety plan; and failing to properly monitor water quality. In 2018, FERC revoked Boyce’s license. Jurisdiction over the Dam passed to Michigan’s Department of Environmental, Great Lakes, and Energy (EGLE), which regulates over 1,000 dams. EGLE inspected the Dam and found it to be in “fair” condition. In May 2020, the Tittabawassee portion of the Dam collapsed following heavy rain, causing another downstream dam to fail. Thousands of residents (including the Allens) were forced to evacuate. Boyce filed for bankruptcy.The Allens sued under the Federal Tort Claims Act for damages and restitution from the United States, arguing that FERC negligently entrusted Boyce with the Dam. The Sixth Circuit affirmed the dismissal of the case. The United States was entitled to sovereign immunity and did not waive that immunity in the Federal Power Act, 16 U.S.C. 791a–823g. Section 803(c) imposes liability on the licensees who build and manage hydropower projects. View "Allen v. United States" on Justia Law

by
In 2018, the Plaintiffs each purchased real estate in Cleveland, planning to rehabilitate and redevelop the properties. Before those purchases, Cleveland declared the buildings on the properties public nuisances, condemned them, and ordered that they be demolished. Following the purchases, and after the Plaintiffs invested time and resources into renovating the buildings, Cleveland authorized private contractors to demolish them. After the demolition of the buildings, the Plaintiffs sued, arguing that the demolitions violated state laws and federal constitutional provisions. The district court granted the defendants summary judgment on the constitutional claims and declined to exercise supplemental jurisdiction over the state law claims.The Sixth Circuit affirmed. Each Plaintiff received “notice reasonably calculated, under all the circumstances, to apprise interested parties of the pendency of the action and afford them an opportunity to present their objections.” After their purchases, Cleveland sent “new owner letters” via certified mail both to the property address and to each Plaintiff's statutory agent, including both the notice of condemnation and demolition order. Neither Plaintiff applied for required rehabilitation permits. View "First Floor Living LLC v. City of Cleveland, Ohio" on Justia Law

by
Fillmore County Park in Genoa Charter Township, Michigan, includes a 15-station “Leopold the Lion Reading Trail” with large signs, telling the story. On a wooded 40-acre property a few miles away, Catholic Healthcare created a prayer trail with 14 “Stations of the Cross.” None of the improvements were visible from outside the property. The Township treated the prayer trail as a church building, for which a “special land use” permit was required. At considerable expense, Catholic Healthcare submitted two unsuccessful applications. The Township demanded the removal of the Stations of the Cross, plus a stone altar and mural.Catholic Healthcare sought a preliminary injunction to restore the Stations of the Cross, altar, and mural. The district court twice denied that request, holding that its free-exercise and statutory claims are unripe. The Sixth Circuit reversed. In land-use cases, claims are ripe when the government has adopted a “definitive position” as to “how the regulations at issue apply to the particular land in question.” Here, the Township has uniformly insisted that Catholic Healthcare obtain a special land-use permit and has twice refused to grant a permit. Those events have “inflicted an actual, concrete injury” because the Township has actually forced them to remove the religious displays. Catholic Healthcare is likely to succeed on the merits of its claim under 42 U.S.C. 2000cc(a)(1), the Religious Land Use and Institutionalized Persons Act. View "Catholic Healthcare International Inc. v. Genoa Charter Township, Michigan" on Justia Law

by
Freed fell behind approximately $1,100 on his property taxes. Thomas, Gratiot County’s treasurer, foreclosed on Freed’s property and sold it at a public auction for $42,000. The County retained the entire proceeds. Freed sued the County and Thomas under 42 U.S.C. 1983, alleging an unconstitutional taking under the Fifth and Fourteenth Amendments and an unconstitutional excessive fine under the Eighth Amendment.Following a remand, the district court granted Freed summary judgment on his Fifth Amendment claim, rejecting Freed’s argument that he was entitled to the fair market value of his property, minus his debt, and holding that Freed was owed just compensation in the amount of the difference between the foreclosure sale and his debt, plus interest from the date of the foreclosure sale. Freed was owed about $40,900 plus interest, $56,800 less than he was seeking. The court also held that Freed’s claims against Thomas were barred by qualified immunity and denied Freed’s subsequent motion for attorney’s fees. The Sixth Circuit affirmed. Following a public sale, a debtor is entitled to any surplus proceeds from the sale, which represent the value of the equitable title extinguished. Thomas did not violate a right that was clearly established at the time of her alleged misconduct. View "Freed v. Thomas" on Justia Law

by
Three individuals filed suit under 42 U.S.C. 1983, alleging that Wayne County has a policy or practice of seizing vehicles and their contents without probable cause, simply because of the vehicle’s location in an area generally associated with crime. Wayne County impounds the vehicles and their contents until the owner pays a redemption fee: $900 for the first seizure, $1,800 for the second, and $2,700 for the third, plus towing and storage fees. The owner's only alternatives are to abandon the vehicle or to wait for prosecutors to decide whether to initiate civil forfeiture proceedings. Before a forfeiture action is brought, there are multiple pretrial conferences involving the owner and prosecutors, without a judge; prosecutors attempt to persuade the owner to pay the fee by pointing out that storage fees accrue daily. Missing just one conference results in automatic forfeiture. It takes at least four months, beyond any previous delays to arrive before a neutral decisionmaker. The seizure proceedings are conducted under Michigan’s Nuisance Abatement statute, the Controlled Substances Act, and the Omnibus Forfeiture Act, which do not protect plaintiffs from the pre-hearing deprivation of their properties.The Sixth Circuit held that Wayne County violated the Constitution when it seized plaintiffs’ personal vehicles—which were vital to their transportation and livelihoods— with no timely process to contest the seizure. Wayne County was required to provide an interim hearing within two weeks to test the probable validity of the deprivation. View "Ingram v. Wayne County, Michigan" on Justia Law

by
In 2016, Salansky, the Great Smoky Mountains National Park’s Fire Management Officer, discovered a slow-moving fire covering less than an acre. Due to the upcoming Thanksgiving holiday, most of the Park’s staff were away. Eight days later (November 24), Salansky observed that building a fire line would be impossible. Salansky opted to let the fire burn, using the natural terrain for containment. On November 27, Salansky requested additional firefighting resources. A National Guard helicopter dropped water onto the fire. By evening, the fire had spread to 35-40 acres within Park boundaries. Salansky did not monitor the fire overnight. At 4:05 a.m., the National Weather Service issued a high-wind warning. By 7:30 a.m., Salansky estimated that the fire had grown to 250-500 acres. Burning embers created smaller fires a mile away. People in Gatlinburg observed heavy smoke and ash. A 10:58 a.m. call was the first communication between Park staff and any local official about the fire. Around 5:45 p.m., the Gatlinburg Fire Department received reports of fires within the city. Winds gusted to 87 mph and the fire grew to 5,000 acres. Total evacuation of the Gatlinburg area was ordered. Evacuation efforts were hampered by infrastructure damage. Ultimately, 14 people died, 191 were injured, 2,500 structures were damaged or destroyed, and more than 17,000 acres burned.The Sixth Circuit vacated the dismissal of “failure to warn” suits under the Federal Torts Claims Act (FTCA). Before filing suit under the FTCA, a claimant must “present” that claim to the agency, 28 U.S.C. 2675(a); the plaintiffs’ forms sufficiently enabled the Department of the Interior to investigate. On remand, to determine whether the claims are barred by the FTCA's discretionary-function exception, the district court should address whether certain publications constitute mandatory directives. View "Abbott v. United States" on Justia Law

by
International sought permission to erect two two-sided billboards in the City of Troy. These billboards were to be 14 by 48 feet in area and 70 feet in height when mounted; they did not conform to height, size, and setback requirements in the Ordinance. After the City denied its permit application and request for a variance, International sued, citing the First Amendment and arguing that the Ordinance’s variance procedure imposed an invalid prior restraint and that its permit exceptions were content-based restrictions on free speech. The Sixth Circuit affirmed summary judgment to the City on International’s prior-restraint claim but remanded for the court to consider whether the Ordinance, with the permit exceptions, survived strict scrutiny.The district court held that the permitting requirements, with the content-based exceptions. did not survive strict scrutiny but that the permit exceptions are severable, leaving intact the Ordinance’s height, size, and setback requirements. The Sixth Circuit affirmed. International’s proposed billboards do not satisfy those valid, content-neutral standards, View "International Outdoor, Inc. v. City of Troy" on Justia Law